Enter the hours and work status in the My Day component.


Start

By default, you enter the hours for the current day, but you can change the day by selecting a particular day (1) or clicking on the "<" buttom to show the previous day.


Select your Project (not displayed in the screenshot) , Activity Type, etc.  and the Work Status.


If you click Start (2) you check in.  You can optionally overwrite the start/check-in time.


Update - Stop - Switch

Once started, you can see the start time, but the Hours still show 0 (1) - you can see/update the time since check-in in (2) and you can also update it.


You have the option to 

  • Update the information, e.g. project, activity type, description, etc.
  • Stop the time and optionally provide a End (check-out) time
  • Switch Status

When switching the status you can

  • Update any information
  • Select the new status (here Break)
  • Overwrite the End (check-out) time

 The current record is then completed and a new record created - copying the project, activity type, etc.


Next ... start break

After switching (or stopping and starting) the day history is displayed - here 3h (1)

The time after the last check-in is displayed in (2)


Next ... end break

Here I ended my break and continued working


So, I am back working after finishing the previous Work and Break - 3.5h (1)

... and according to the info worked 3.4h since then (2)


In the Compliance section, I can see the detail rules as well as my compliance status:

  • 3 hours work
  • 30 minutes break, but I need 4 hours work to have the break required.


End - Check-Out

After my final Check-Out

in (1) I see that I worked 11 hours (8.00h work + 3.00h overtime), I had the required meal, but not the second required break.


I can now also select any of the previous time slots (2) and update the record.